Photos from a recent site visit to this new Modern Modular project in East Hampton; construction will wrap up within the next few months. The pool’s been poured. Decks are being constructed this week; ipe decking was delivered while we were there. Stucco ceiling work will continue next week, which will have a big impact, lightening the covered spaces considerably. Custom stair fabrication is also in progress. We can’t wait to see those skylights in a finished space!
See more of the project here: https://www.re4a.com/in-progress#/great-oak-residence/